Phase One, dedicated to the storage of glycol, LPG, and methanol products, comprises 32 storage tanks as detailed below, which have now been constructed:
Glycol: Two MEG storage tanks, two DEG storage tanks, and two TEG storage tanks
LPG: Two propane storage tanks and one butane storage tank
Methanol: Four methanol storage tanks
The remaining Phase One facilities include eight methanol storage tanks and five glycol storage tanks. At present, six methanol tanks and three glycol tanks have been awarded to an EPC contractor for construction and, according to the project schedule, are expected to become operational by the end of 1400.
The award of the remaining two methanol storage tanks and two glycol storage tanks is currently at the initial contractor selection stage.
It should also be noted that Phase Two of Asaluyeh Petrochemical Green Storage Company is dedicated to products manufactured by Kian Petrochemical Company. Following the commencement of construction of that petrochemical complex, preliminary correspondence regarding the requirements of Phase Two of Asaluyeh Petrochemical Green Storage Company is currently underway.